Task requiring more resources #129

@davideschiavone

Description

@davideschiavone

Dear all,

thanks a lot for the work you have done! amazing!

Quick question, I am trying the Resource constrained project scheduling example, and I would like to know whether you will provide a way to solve a problem where one job requires more resources than the one provided.

For example, the JOB1 requires 5 C1 resources over a total of 6 C1 resources.

If it requires 8 resources, the program fails - but it could solve this by first satisfying the first 6, then the last 2 (time multiplexing).

This can be done by defining a new job "1B" that depends on the job "1A" where I separate by hand the 2 jobs - but this fails in having the whole picture view (i.e. other jobs scheduled and mapped in parallel) as maybe it would be better to do first 3 C1 jobs and then the remaining 5 (because in parallel some other job are also needing C1).

Let me know your thoughts,

thanks
Davide

Metadata

Metadata

Assignees

No one assigned

    Labels

    No labels
    No labels

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions