diff --git a/progress-reports/ibc-integration/iBriz-IBC-March-2025-Progress-Update.md b/progress-reports/ibc-integration/iBriz-IBC-March-2025-Progress-Update.md new file mode 100644 index 0000000..1f8fcd7 --- /dev/null +++ b/progress-reports/ibc-integration/iBriz-IBC-March-2025-Progress-Update.md @@ -0,0 +1,59 @@ +# IBC - March 2025 Progress Update + +## Intro +This progress report is for IBC Integration related development work by iBriz Team. +The next phase of the project will Intent and Solver development with Relay V3. The report is from 1-March-2025 to 31-March-2025 + +## Summary +For more details please see :
+https://github.com/icon-project/IBC-Integration
+https://github.com/icon-project/ibc-relay
+https://github.com/icon-project/xcall-multi
+https://github.com/icon-project/centralised-relay
+https://github.com/icon-project/intent-relay
+https://github.com/icon-project/Icon-network-solver
+https://github.com/icon-project/intent-contracts + +## Milestones +Milestone 1 - Testnet Deployment on Archway and ICON - 11th August 2023 - Completed
+Milestone 2 - Testnet Deployment - ICON - Libson, Archway and Neutron - 12th September 2023 - Completed
+Milestone 3 - Mainnet Deployment - ICON and Archway - 6th October 2023- Completed
+Milestone 4 - Mainnet Deployment - IBC Neutron - 31st October 2023- Completed
+Milestone 5 - Mainnet Deployment - IBC Injective - 5th January 2024 - Completed
+Milestone 6 - Centralised Relay for Avalanche and ICON - 19th January 2024 - Completed
+Milestone 7 - xCall deployments for Wormhole and LayerZero - 5th February - Completed
+Milestone 8 - Centralised Relay integration for Archway - 29th March - Completed
+Milestone 9 - Hopchain and ICS20 Integration to IBC - TBD - In Progress
+Milestone 10 - xCall on SUI - August 2024 - Completed
+Milestone 11 - xCall on Neon EVM - TBD - On Hold
+Milestone 12 - xCall on Stellar - September 2024 - Completed
+Milestone 13 - xCall on Solana - September 2024 - Completed
+Milestone 14 - Swap Intent - December 2024 - In Progress
+Milestone 15 - Relay Cluster - December 2024 - Deployments in Progress
+ + +## Deliverables Ready + +| Name | Development State | Notes | Source / location | +|:----- |:------------------ | :----| :----------------| +| Relay Cluster | Deployment Ready | Centralized Relay V2 - Mainnet Deployments. Only SUI remaining to migrate to cluster | https://github.com/icon-project/ibc-planning/issues/495 | +| Swap Intent | Deployment Ready | Swap Intent - Deployed on SUI and EVM. All contracts testing completed. Stellar and ICON completed. Solana testing in progress. | https://github.com/icon-project/ibc-planning/issues/494 | +| Relay V3 | Completed | Relay v3 Audit and Fix Completed. Deployed to Mainnet on EVM | https://github.com/icon-project/intent-relay/issues/1 | +| Asset Managers | Audit and Deployment | Internal Audit Completed for EVM, Cosmos and SUI. Solana and Stellar in Progress | https://github.com/orgs/icon-project/projects/12/views/2?sliceBy%5Bvalue%5D=Asset+managers | + + +## Deliverables Projected for Next Cycle + + +| Name | Development State | Notes | +|:-----|:------------------|:------| +| Swap Intent | Development | Swap Intent - Injective and Arbitrum | +| Relay V3 | Deployment | Continue deployment on non EVM chains - https://github.com/icon-project/intent-relay/issues/1 | +| Asset Managers | Audit and Deployment | Audit Fix and Mainnet Deployment for Solana and Stellar https://github.com/orgs/icon-project/projects/12/views/2?sliceBy%5Bvalue%5D=Asset+managers | + + +## Sample of docs +https://github.com/icon-project/IBC-Integration
+https://github.com/icon-project/ibc-relay
+https://github.com/icon-project/xcall-multi
+https://github.com/icon-project/centralised-relay